Turnkey · Factory tested · Delivered across Europe

Container data centres, delivered ready to run.

A complete modular data centre in one factory-built enclosure, tested before it ships and running on your site in weeks, not years.

  • 25 to 150 kWIT load
  • 12 to 14 weeksOrder to site
  • 2N or N+1Power and cooling
Inside a container data centre: a row of 42U server cabinets with yellow fibre trays above and red fire suppression pipework

The problem

Why not build a server room?

A conventional server room takes 12 to 24 months, needs a building, permits and several contractors, and stays where it is built.

Nowhere to build

No suitable room, or the current building is due for refurbishment.

Too slow

Capacity is needed this year, not in two years.

Data must stay on site

Production, defence or patient data that cannot leave the site.

The room cannot take the load

Old rooms handle 3 to 5 kW per rack. Today's IT needs far more.

The site may move

A container goes back on a truck. A building does not.

A second site is needed

Disaster recovery without leasing a second building.

The solution

One enclosure, one contract, tested before it ships

Power, cooling, fire, monitoring, security and cabling, assembled and load tested in the factory, then commissioned on site in 7 to 10 days.

3D cutaway of a container data centre showing the cabinet row, in-row cooling, UPS and fire suppression inside one enclosure

Power

2N or N+1. Modular lithium-ion UPS, about 15 minutes autonomy, two monitored PDUs per cabinet.

Cooling

In-row DX precision cooling, N+1, hot aisle containment. Free cooling option for Nordic and Baltic sites.

Fire protection

Novec 1230 suppression and smoke detection to EN 15004 and EN 54. VESDA as an option.

Monitoring

DCIM, temperature, humidity, leak and door sensors. SNMP and Modbus to your BMS, email and SMS alarms.

Security

Card and PIN access, IP CCTV, no windows, sealed cable entries. RC4 (EN 1627) as a hardened option.

Cabling

24 copper and 24 fibre links per cabinet, separated copper, fibre and low voltage routes.

Full technical specificationContainer or new server room?

Key figures and reference

100 kW, ten cabinets, running as a primary facility

One reference unit carries an organisation's primary IT operation. It was specified, built, installed and commissioned under one contract.

IT load range25, 50, 75, 100 and 150 kW
Reference unit100 kW, 10 × 42U cabinets (800 × 1100 mm)
Rack density10 to 15 kW standard, up to 20 kW air cooled
Redundancy2N or N+1 power, N+1 cooling
Enclosure13,550 × 3,200 × 2,900 mm, IP55, 43.4 m² inside
EfficiencyMeasured PUE 1.3 to 1.4 in operation
Lead time12 to 14 weeks from order to site
Warranty2 years, including maintenance
Container data centre on its prepared concrete slab with condensers on integrated end frames
12 weeksOrder to delivery
1 weekendFull IT migration
~1,200Fibre connections
4/8/24 hResponse, intervention, resolution

Service levels met in operation. Further references and the full engineering package are available under a non-disclosure agreement.

See the reference installationContainer data centre price

Use cases

Where container data centres are used

Edge for factories

Vision inspection, robotics and plant analytics next to production.

Defence and public sector

Restricted data with security specified to your regime.

Disaster recovery

A second physical site without a new building.

Private AI and GPU

On-site inference where data must stay under your control.

Telecom and remote sites

Edge processing at telecom, energy and isolated locations.

Temporary capacity

During refurbishment or relocation, then move the unit.

You choose the brands

Specified around the equipment you already run

Existing maintenance contracts, spares and engineer training continue to apply.

UPS
Vertiv, Schneider Electric, Eaton, Socomec, Legrand
Cooling
Vertiv, Stulz, Schneider Electric
Cabinets
Vertiv, Rittal, Schneider Electric, Panduit
Cabling
CommScope, Corning, Panduit
Switchgear
Siemens, ABB, Eaton, Legrand

Designed to EN 50600 principles and ASHRAE thermal guidelines, fire protection to EN 15004 and EN 54, all equipment CE marked. Redundancy is designed to the Tier level you choose; Uptime Institute certification is available as an option.

How it works

How a project works

Typically 12 to 14 weeks from order to a running facility.

  1. Day 1

    Send load, site, date

    Three figures are enough.

  2. 48 hours

    Budget price

    With an outline configuration.

  3. Before build

    Drawings

    Elevations, single lines, specification.

  4. 12 to 14 weeks

    Build and test

    Load bank test in the factory.

  5. On site

    Commissioning

    Installed in 7 to 10 days.

FAQ

Container data centre questions

More answers in the full FAQ and the price guide. Or ask us directly: we reply within a few hours.

Request a budget price

What is a container data centre?

A container data centre, also called a modular, containerised or prefabricated data centre (container data center in US English), is a complete data centre built inside a factory-made enclosure. Power, cooling, fire suppression, monitoring and cabling are installed and tested before delivery, so the unit only needs a slab, power and fibre on site.

How long does delivery take?

Typically 12 to 14 weeks from order to site for a standard configuration, including the factory acceptance test. Installation and commissioning on site usually take 7 to 10 days.

What do we need to prepare on site?

A prepared concrete slab, a power feed and a fibre connection. For the 100 kW reference unit the slab is 5,200 mm wide and the unit is 19,550 mm long including the condensers.

How much does a container data centre cost?

Turnkey units are typically budgeted at about €8,000 to €10,000 per kW of IT load, so a 100 kW unit usually lands between €0.8M and €1.0M. Redundancy, cooling, security level and site scope move the figure. Send us your IT load, site and date for a budget price.

Can we choose the equipment brands?

Yes. UPS, cooling, cabinets, cabling and switchgear can be specified from the brands you already run, so existing maintenance contracts, spares and engineer training continue to apply.

Do you supply the servers?

No. The client supplies its own servers, storage and network equipment. The unit is delivered ready for your IT hardware.

Budget price

Request a budget price

Three figures are enough to start: IT load, site and date. We reply within a few hours, with a budget price within 48 hours.

48hBudget price and an outline configuration. Specification and drawings follow once the scope is agreed.
Reply within hours · budget price within 48 hours
Request a budget price