Delivered configuration
Reference installation: 100 kW, ten cabinets, primary facility
One unit carries an organisation's primary IT operation rather than a test or overflow load. It was specified, engineered, built, installed and commissioned under a single contract.
- 12 weeksOrder to delivery
- 1 weekendFull IT migration
- ~1,200Fibre connections

Delivered configuration
What was delivered, and how it performed
| IT load | 100 kW |
|---|---|
| Server cabinets | 10 × 42U |
| UPS | 2 units, N+1, lithium-ion |
| Precision cooling | 5 in-row units, N+1 |
| Fire suppression | Novec 1230 |
| Standby generator | Included |
| Enclosure | IP55, seismically isolated |
| Delivery from order | 12 weeks |
|---|---|
| Installation on site | 7 to 10 days |
| IT migration | One weekend |
| Fibre connections | About 1,200 |
| Operational role | Primary facility |
| Service levels met | 4 h response, 8 h intervention, 24 h resolution |
| Warranty and maintenance | 2 years |
Further references and the full engineering package are available under a non-disclosure agreement.
Photos
The unit on site and in operation



Budget price
Request a budget price
Three figures are enough to start: IT load, site and date. We reply within a few hours, with a budget price within 48 hours.
Phone+372 5355 0574
48hBudget price and an outline configuration. Specification and drawings follow once the scope is agreed.